Material-at-Site Statement
Monthly statement of materials brought to site but not yet incorporated. Basis for Cl. 43 secured advance claims on steel, bitumen, and cement.
When to use this letter
With each RA bill, when steel, bitumen, cement, or other bulky materials sit on site awaiting incorporation. Secured advance under Cl. 43 frees up working capital tied in stockpiles.
What's inside
- Material category with cumulative receipt quantity
- Quantity consumed and balance at site
- Storage location and inspection certificate references
- Insurance and custody undertaking
- Cl. 43 secured advance computation
Why this is different from a generic template
Related templates
Daily Site Diary
Daily progress report covering: resources deployed (labour/plant), work executed by chainage, weather, instructions received, and hindrances. Accepted format for NHAI IRC road packages.
Hindrance Register
Running register of site hindrances: date, nature of hindrance (land, utility, employer instruction), impact on programme, and closure date. Admissible evidence in arbitration.