Hindrance Register
Running register of site hindrances: date, nature of hindrance (land, utility, employer instruction), impact on programme, and closure date. Admissible evidence in arbitration.
When to use this letter
Throughout construction. Each hindrance gets a serial number on the day it surfaces, not at the end of the month. The register is the most-cited contemporaneous record in NHAI dispute proceedings.
What's inside
- Hindrance serial number and date opened
- Nature of hindrance categorised (land, utility, drawing, instruction, force majeure)
- Location reference by chainage or structure
- Impact paragraph: on-site activity halted, manpower diverted
- Closure date and intervening period
- Reference to corresponding letter or notice issued
Why this is different from a generic template
Related templates
Daily Site Diary
Daily progress report covering: resources deployed (labour/plant), work executed by chainage, weather, instructions received, and hindrances. Accepted format for NHAI IRC road packages.
Material-at-Site Statement
Monthly statement of materials brought to site but not yet incorporated. Basis for Cl. 43 secured advance claims on steel, bitumen, and cement.