Hindrance Register

Running register of site hindrances: date, nature of hindrance (land, utility, employer instruction), impact on programme, and closure date. Admissible evidence in arbitration.

When to use this letter

Throughout construction. Each hindrance gets a serial number on the day it surfaces, not at the end of the month. The register is the most-cited contemporaneous record in NHAI dispute proceedings.

What's inside

  • Hindrance serial number and date opened
  • Nature of hindrance categorised (land, utility, drawing, instruction, force majeure)
  • Location reference by chainage or structure
  • Impact paragraph: on-site activity halted, manpower diverted
  • Closure date and intervening period
  • Reference to corresponding letter or notice issued
HindranceDelay RecordsEvidence

Why this is different from a generic template

Clause numbers, not vague rights
Cites General directly. Generic templates skip the clause reference and lose the legal anchor.
Indian contract context
Written for NHAI, CPWD, and MoRTH practice. Not a FIDIC document with Indian terminology pasted over it.
Evidence-ready structure
Notice periods, delivery method, and acknowledgement trail built in. Stands up at DRB and arbitration.

Skip the blank page. CivilBolt drafts this with your contract clauses filled in.

Upload your contract and CivilBolt produces a hindrance register with the right clause references, notice periods, and delivery obligations already populated. Edit the specifics, send it out.